HomeMy WebLinkAboutMinutes - CTHBC - 08/29/2017 Town Hall Renovation Advisory Committee Meeting Wilcutt Commons 91 Sohier Street Cohasset, MA 02025 8/29/2017 In attendance: Mary McGoldrick, Chair Carolyn Coffey Fran Collins Tom Reardon Josiah Stevenson Mark Toomey Sam Wakeman Chris Senior, Town Manager Shane Nolan, OPM Wendell Kalsow, MK&A Doug Manley, MK&A Megan Sherck, MK&A Missing: Brian Joyce, DPW The meeting was called to order at 6:45pm. Mary McGoldrick asked for a motion to approve the minutes from 08/01/17 with the following correction; Paragraph 2 to read, "Sam Wakeman requested the Committee to take into consideration the potential future use of the Town Hall space in its deliberation." Carolyn Coffey motioned to approve the minutes as amended. Fran Collins seconded the motion. Doug Manley began the discussion with the building schemes for Option 3 (Renovation of Historic Town Hall with addition attached) and Option 4 (Renovation of Historic Town Hall and new detached building). The programming study was presented for each option. Massing studies were presented for Option 3 and Option 4. Shane Nolan presented the cost estimates for Option 3 and Option 4. Estimates included numbers from both Daedalus Projects and McGinley Kalsow/DG Jones. A comparison was made between the estimated costs for Options 3 &4. Estimates include the premium to achieve a LEED certified rating. There is a 15.97% increase in the cost for Option 4. Shane Nolan presented a Cost/SF comparison of recently constructed Town Hall projects that included: renovations, renovation/addition, and demolition and new construction. The Cost/SF ranged from $354-489. (All costs were adjusted to Q2 2018 dollars using Turner Building Cost Index). Cohasset Town Hall Option 3 is estimated to be $382 Cost/SF. Cohasset Town Hall Option 4 is estimated to be $408 Cost/SF. For Option 3: $1,050,000 would be requested at Special Town Meeting on October 16, 2017 for the design and bidding phase, $11,750,000 would be requested at Annual Town Meeting in the spring of 2018. The anticipated total project budget for Option 3 is $12,800,000. For Option 4: $1,180,000 would be requested at Special Town Meeting on October 16, 2017 for the design and bidding phase, $13,420,000 would be requested at Annual Town Meeting in the spring of 2018. The anticipated total project budget for Option 4 is $14,600,000. Wendell Kalsow then presented preliminary eligibility for CPA funding for Options 3 and 4. After much discussion the Committee voted unanimously to approve an attached addition. The Committee decided not to vote on any other item related to project design until they had time to review concerns from both the audience members and Committee members regarding improvements to the aesthetic appeal of the building. The Committee agreed to postpone the presentation before the joint meeting of the Board of Selectman, Capital and Advisory on September 5, 2017. Instead, the Committee agreed to present before the Board of Selectman on September 12, 2017. Some community members wondered if the Committee should ask the Town to approve the estimated budget for Option 3 outright at Special Town Meeting in October. Some members of the Committee concurred. Those for the proposed idea cited the risks of spending$1million in design fees for a project that may not receive Town approval at Annual Town Meeting. Mary McGoldrick pointed out that large capital items tend to be discussed at Annual Town Meeting and more public education on the project is needed. The meeting was adjourned at 9:45.